What Is a Tremie? Tremie Pipe and Tremie Concrete Explained

A tremie is a vertical pipe, fitted with a hopper at the top, that carries concrete to the bottom of a hole filled with water or slurry so the concrete does not mix with the fluid. This guide explains what a tremie pipe is, how tremie concrete is placed in a bored pile, and what goes wrong when the pour is not controlled.

Quick Answer

A tremie pipe is lowered to the bottom of a drilled shaft after the reinforcement cage is in place. Concrete is fed through the hopper and flows down the pipe by gravity, pushing the water or slurry up and out as the pile fills from the bottom. The pipe outlet must stay buried in the fresh concrete the whole time, and the pour must be continuous. If the outlet leaves the concrete, fluid enters the pile and creates weak zones. The project specification sets the pipe size, concrete mix and embedment depth.

What Is a Tremie?

A tremie is a placing method and a piece of equipment: a vertical pipe through which concrete is discharged at the bottom of a hole or excavation that holds water or drilling slurry. The word comes from the French for hopper, which is the funnel fitted at the top of the pipe.

In everyday site talk, “the tremie” means the pipe, and “tremie concrete” means the concrete placed through it. Dropping concrete through water or slurry from the top washes the cement out and separates the aggregate. The tremie avoids that by delivering the concrete below the fluid, where it can push the fluid aside.

The same method also forms underwater slabs, called tremie seals, inside cofferdams. This guide covers the use that matters to bored pile contractors: concreting the pile shaft after the hole has been drilled.

Where Is a Tremie Used?

A tremie is used wherever concrete must be placed below a fluid level. In foundation work that usually means these cases:

  • Bored piles and drilled shafts that are full of water or slurry.
  • Diaphragm walls and secant pile walls built under slurry.
  • Bridge piers and marine foundations in rivers or sea water.
  • Tremie seal slabs poured underwater inside cofferdams.

Bored piles are also called drilled shafts or drilled piers, and large-diameter ones are sometimes called caissons. The method described here applies to the first case in the list above: a rotary-drilled shaft that is concreted from the bottom up.

Parts of a Tremie Pipe System

A tremie pipe system is a string of steel pipe sections with a hopper at the top and a plug or seal at the bottom. The table lists the parts you will find on most systems.

PartWhat it does
Pipe sectionsSteel tubes, often 1 to 3 m long, joined to reach the base of the hole and removed one by one as the pour rises
Joints or couplingsConnect the sections and must be watertight so slurry cannot enter
HopperThe funnel at the top that receives concrete from the pump, chute or truck
Lifting capThe top fitting that the crane uses to hold and raise the string
Plug (pig) or sealed gateKeeps water or slurry out of the pipe until the first concrete arrives
Bottom sectionThe lowest length, which meets the most wear and discharges at the base of the pile

Tremie Pipe Joints and Sizes

The three common joint types are threaded, flanged and quick coupling. Threaded joints are simple and strong. Flanged joints bolt together and take longer to assemble. Quick couplings are the fastest to fit, but they need a good seal and regular inspection.

Pipe size follows the pile and the concrete. Several state transportation specifications call for a pipe at least 10 inches (about 250 mm) in diameter, and at least six times the size of the largest aggregate. Aluminum parts should not touch the concrete, because aluminum reacts with the cement.

How Does a Tremie Pipe Work?

A tremie pipe works by keeping the concrete inside a closed, full pipe until it is below the surface of the fluid, and then letting it flow out at the bottom. Gravity moves the concrete down, and the rising concrete pushes the lighter fluid upward.

  • Seal: the plug or gate stops water or slurry from entering the pipe, or separates it from the first batch.
  • Fill: the hopper and pipe are filled with concrete, and the plug or seal is released at the bottom.
  • Flow: concrete leaves the pipe at the base of the hole and moves outward and upward, displacing the fluid.
  • Embed: the outlet stays buried in the fresh concrete, so only concrete, never fluid, meets the concrete in the pile.
  • Lift: as the level rises, the pipe is raised slowly and sections are removed, while the outlet stays buried.

Once the concrete is flowing, one rule decides the rest of the pour.

Keep the outlet below the surface of the fresh concrete.

One state specification asks for the discharge end to stay 5 to 10 feet (about 1.5 to 3 m) deep in the concrete before the pipe is lifted, and other sources quote values in a similar range. Your project specification gives the number to follow.

Tremie Concrete Pour in a Bored Pile: Step by Step

A tremie concrete pour is the last stage of bored pile construction, and the hole must be right before it starts. The usual order is as follows.

  1. Drill the shaft. The rig drills to the design depth and diameter; the crew checks depth, diameter and plumb.
  2. Clean the base. Loose soil and sediment are removed from the bottom, because anything left there ends up in the pile.
  3. Place the cage. The reinforcement cage is lowered in, centered with spacers, and held down against lifting.
  4. Check again. The depth is measured after the cage is set; if sediment has settled, the base is cleaned again.
  5. Lower the tremie. The string is assembled and lowered until the outlet is just above the base of the hole.
  6. Seal and charge. The plug or gate is set, and the hopper and pipe are filled with concrete.
  7. Start the flow. The pipe is lifted slightly so the plug is released and the concrete flows.
  8. Pour continuously. The outlet stays buried while the pipe is raised and sections are removed.
  9. Finish. The pour continues until good concrete flows out at the top, and any casing is withdrawn slowly while concrete stays above it.

The pour has to run above the final cut-off level. The top of the pour collects sediment and weak concrete that must be cut away, so the pile needs sound concrete up to the level the design requires.

Dry Hole or Wet Hole?

A tremie is needed when the hole is wet, and it is optional when the hole is dry. Dry holes stay free of water and do not cave in, and wet holes hold water or slurry that supports the walls or cannot be pumped out.

ConditionTypical situationHow concrete is placed
Dry holeWater table below the base, stiff soil that does not caveConcrete can be dropped through a centering chute, if the specification allows it
Wet hole, slurry-supportedHigh water table or sandy soil that would caveTremie pipe or concrete pump pipe to the base
Wet hole, with casingCaving soils with water, casing advanced with the drillingTremie or pump pipe, with the water in the casing displaced by the concrete

Drilling fluid and casing choices belong to the contractor and designer. Specifications also vary on whether water, polymer or bentonite slurry is allowed, so follow the project documents.

What Concrete Works with a Tremie?

Tremie concrete must flow easily, resist segregation and stay workable for the whole pour. It flows through the pipe and the cage by gravity, so a stiff mix will block the pipe or leave voids around the steel.

State drilled shaft specifications typically set a high target slump, often in the 8 to 9 inch range (about 200 to 230 mm). They also require the slump to stay above a minimum, commonly about 4 inches (100 mm), until the pour is finished. Retarders are used on long pours so that the concrete does not stiffen before the pour ends.

The concrete supply must be planned too. Trucks need to arrive on schedule so the pour is not interrupted, and the contractor should know the volume needed for the pile before it starts.

What Goes Wrong with a Tremie Pour

Most tremie pour defects come from a lost seal, a stopped pour or poor concrete. The table shows the common problems and what prevents them.

ProblemTypical causeHow to prevent it
Slurry or sediment inside the pilePipe outlet lifted out of the concreteTrack the concrete level and the pipe length, and keep the outlet buried
Blocked pipeStiff or low-slump concrete, or a stopped pourKeep the slump up and supply the concrete continuously
Voids or honeycombConcrete too stiff, or the cage too tight for the aggregateCheck the mix and the bar spacing before the pour
Cage lifted or shiftedCage not held down, or the pipe lifted too fastHold the cage down, and raise the pipe slowly
Weak concrete at the baseSediment left at the bottom of the holeClean the base, and clean again after the cage is set
Pile narrower than designCasing pulled too fast, or concrete level droppedKeep a head of concrete above the casing, and stop and add concrete if the level falls

If the pipe does leave the concrete, one state specification requires the end to be re-sealed, filled with concrete and pushed back into the concrete by at least 10 feet before pouring continues. Whether the pile is accepted is then decided by the engineer and by testing.

Checks Before and After the Pour

Most defective piles are caught by checking before the pour and recording during it. The checks below follow what many agency specifications ask for.

WhenWhat to check
Before drilling endsDepth, diameter and plumb, using marks on the kelly bar and a plumb check
Before the cage goes inBase cleanliness, using a weighted tape to measure sediment, and slurry condition
Before the pourCage held and centered, pipe watertight and sealed, concrete supply and slump confirmed
During the pourConcrete level and outlet depth, with a weighted tape, plus the volume delivered
After the pourPlaced volume against the theoretical volume of the shaft, which can reveal voids
On the finished pileIntegrity testing, such as pulse echo or cross-hole sonic logging, and coring or load tests when specified

Keep a pour log with the time, truck volume, slump, the length of pipe in the hole and the measured depth to concrete. The FHWA drilled shaft construction manual (FHWA-NHI-10-016) sets out many of these checks in detail.

Tremie vs Free Fall vs Pump

The three ways to place concrete in a shaft are free fall, a tremie pipe, and a concrete pump with a pipe to the base. The table compares them.

MethodWhere it worksMain limit
Free fallDry holes only, through a centering chuteConcrete must not hit the walls or the cage, and the fall height is limited
Tremie pipeWet and dry holes, cased or uncasedNeeds a crane to hold the string, and the outlet must stay buried
Pump pipe to the baseWet and dry holesNeeds watertight joints, and sway of the pipe must not disturb the fresh concrete

A pump pipe is used much like a tremie, so the same embedment rule applies. Many sites feed the tremie hopper from a pump or a concrete bucket.

Handling, Cleaning and Safety

A full tremie string is heavy, so the crane, lifting cap and lines must be rated for the pipe, the concrete inside it, and the loads while the string is lifted. Check the rating before the first pour, not during it.

  • Clean the pipe straight after the pour, because concrete that sets inside narrows the bore and blocks the next pour.
  • Inspect the joints, seals and bottom section for wear before each use.
  • Keep the inside of the pipe smooth so concrete flows and the pipe lifts out freely.
  • Keep people clear of the pipe while it is lifted, and use proper lifting points.
  • Protect open shafts with covers or fencing and a fall plan, because the hole stays open until the pour is done.

Where the Rig Ends and the Tremie Begins

The rotary rig makes the hole, and the tremie fills it, so the quality of the hole sets what the tremie can achieve. The rig controls the diameter, the depth, the position and the plumb of the shaft, and the cleaning bucket prepares the base.

A well-drilled hole makes the pour easier: a straight shaft lets the cage hang centered, and a clean base keeps sediment out of the concrete. The kelly bar carries the tool and shows the depth, as described in our guide to the kelly bar, and the types of bored pile are covered in types of piling.

Kaiao builds the drilling side. The table shows the rated ranges of two of our crawler rigs. These are maximum rated values, and the real depth depends on the bar configuration and the ground.

RigHole dia. / depthTorqueWeight
Large crawler foundation rigΦ1800 mm / 40–50 m150–170 kN·m42–50 t
Interlocking kelly bar rig, crawler typeΦ1500–2200 mm / 15–35 m70–170 kN·m23–33 t

See the foundation drill rig for the large rig, and the wider range under rotary drilling rig. Tengzhou Kaiao Construction Machinery Co., Ltd. makes the drilling equipment only. Tremie pipes, concrete and the pour itself are the contractor’s part of the job.

About Kaiao

Kaiao factory and workshop overview in Tengzhou, Shandong Kaiao workshop welding, machining and assembly areas

Our own factory in Tengzhou, Shandong: development, production, sales, after-sales and custom work all happen under this roof.

  • Started in 2004, more than twenty years building piling equipment
  • Kaiao holds ISO 9001 and CE certification
  • More than 1,000 units a year for five years in a row
  • Development, production, sales, after-sales service and custom work all happen in our own factory
Kaiao ISO 9001 and CE certificates Kaiao patent certificates

ISO 9001 and CE certification, plus patents that include wireless remote control and automatic drilling on rotary rigs.

Learn more about Kaiao.

Tremie FAQ

Tremie basics

What is a tremie?

A tremie is a vertical pipe with a hopper at the top that delivers concrete to the bottom of a hole or excavation filled with water or slurry. The concrete flows out below the fluid and pushes it aside, so the cement does not wash out. The name comes from the French word for hopper.

What is a tremie pipe?

A tremie pipe is a string of steel pipe sections, joined with watertight couplings, that is lowered to the base of a bored pile or similar excavation. A hopper at the top receives the concrete, and a plug or seal at the bottom keeps fluid out until the first concrete arrives. Sections are removed as the pour rises.

What is tremie concrete?

Tremie concrete is concrete placed through a tremie pipe below the level of water or slurry. It needs a high slump, a mix that resists segregation, and a supply that does not stop. State drilled shaft specifications typically set a target slump around 8 to 9 inches and require it to stay above about 4 inches during the pour.

Pour control

Why use a tremie instead of dropping concrete into the hole?

A tremie is used because concrete dropped through water or slurry washes out and separates, which weakens the pile. The pipe delivers the concrete at the base, where it pushes the fluid upward. In a dry hole, a centering chute may be allowed, but a wet hole needs a tremie or a pump pipe.

How deep should the tremie pipe stay in the concrete?

The pipe outlet should stay buried in fresh concrete throughout the pour, and the project specification sets the depth. One state specification asks for 5 to 10 feet, about 1.5 to 3 m, before the pipe is lifted, and other sources quote similar values. A weighted tape is used to measure the concrete level.

What size is a tremie pipe?

Tremie pipe size depends on the pile and the concrete, and many state specifications call for at least 10 inches, about 250 mm, and at least six times the largest aggregate size. Sections are often 1 to 3 m long. The pipe must be wide enough for the concrete to flow freely.

What is the plug in a tremie pipe for?

The plug, often called a pig, separates the first concrete from the water or slurry inside the pipe. It slides down ahead of the concrete and is released at the bottom, so the first batch is not diluted. A sealed gate at the bottom does the same job on some systems.

When the pour goes wrong, and choosing a rig

What happens if the tremie pipe comes out of the concrete?

If the pipe outlet leaves the concrete, slurry or water can enter the pipe and mix into the pile, which leaves weak zones. The usual response is to re-seal the pipe, refill it, and push it back into the concrete before continuing. The engineer then decides on testing and acceptance of the pile.

What information do I need to send to choose a rotary rig for bored piles?

You need the target hole diameter and depth, the ground conditions, the groundwater level, the site access and the project destination. With those details, Kaiao can tell you honestly which machine fits. A soil report and site photos make the recommendation more accurate.

Request a Quote

Planning bored piles? Send us the hole diameter and depth, ground conditions, groundwater level, site access and destination, and we will tell you honestly which rotary rig fits.

Need a quote? Chat with us